Civil Engineering
- Excavations, demolition and temporary works
- Removal and crushing of existing silo base top slabs
- Casting of new reinforced silo base slabs
- Stair tower, MCC room, transformer, fan bases and plinths
- Entrance enhancement and enclosures down into 2 tunnels
- Drainage, sumps, pumps and connections
Mechanical Engineering
- 4 x 700tph silo distribution chain conveyors
- 2 x 650tph silo tunnel reclaim chain conveyors
- 2 x 650tph inclined to terminal transfer chain conveyors
- 2 x rows of 5off (10) 11m diameter x 30m high corrugated steel silos
- 3m wide conveyor catwalks and row interconnecting gantries
- 10 sets x 4off bleed valves c/w central motorised bunker slide on each silo
- 10 x 150tph silo sweep dischargers
- 4 x sets of silo fan aeration and temperature monitoring control
- Low level silo base doors allowing operating personal safe man access
- Emergency access/exit fabricated 30m high stair tower
Electrical Engineering
- Complete site wiring, containment, MCC’s within GRP enclosure
- Lighting throughout facility at high, low level and inside tunnels
- Dedicated GRP retained transfer reclaim transformer
- Fully automated software, control and interface with grain terminal
- System operational software commissioning and integration